Reading: AWS emerges as ‘sole bidder’ for HMRC’s £500m datacentre migration project as rivals exit | Computer Weekly
Share
Sign In
Notification Show More
Font ResizerAa
World of SoftwareWorld of Software
Font ResizerAa
  • Software
  • Mobile
  • Computing
  • Gadget
  • Gaming
  • Videos
Search
  • News
  • Software
  • Mobile
  • Computing
  • Gaming
  • Videos
  • More
    • Gadget
    • Web Stories
    • Trending
    • Press Release
Have an existing account? Sign In
Follow US
  • Privacy
  • Terms
  • Advertise
  • Contact
Copyright © All Rights Reserved. World of Software.
World of Software > News > AWS emerges as ‘sole bidder’ for HMRC’s £500m datacentre migration project as rivals exit | Computer Weekly
News

AWS emerges as ‘sole bidder’ for HMRC’s £500m datacentre migration project as rivals exit | Computer Weekly

News Room
Last updated: 2025/10/30 at 3:44 AM
News Room Published 30 October 2025
Share
SHARE

Amazon Web Services (AWS) is the last supplier standing in the controversial £500m race to become the hyperscaler responsible for overseeing a 10-year datacentre exit project for HM Revenue & Customs (HMRC), Computer Weekly has learned.

As previously reported by Computer Weekly, the government tax collection agency needs a hyperscale provider to manage the migration of its on-premise servers from three Fujitsu datacentres to the cloud.

“The objective of the programme is to exit all services from three managed datacentres and decommission any remaining infrastructure within the current contract period of the incumbent datacentre hosting provider (June 2028),” said HMRC in a tender document.

“The … programme has identified that modern hyperscaler cloud technologies would be the preferred solution to transition to, whilst supporting HMRC’s strategic objectives, without affecting business continuity or incurring an unaffordable cost of change.”

HMRC procurement documents state the successful bidder for the contract is expected to be announced in late April 2026, but sources with close working knowledge of the procurement process claim AWS has recently become the only supplier left in the running for the contract.

It was previously confirmed by HMRC in June 2025 that AWS, Google, IBM, Microsoft and Oracle were all approached to participate in the request for information portion of the multi-stage tender process for the deal.

At some point over the past few months, Oracle and Microsoft exited the process, and AWS, Google and IBM were provisionally shortlisted. “There were three big providers selected and provisionally down-selected for the tender, which was AWS, IBM and Google … but IBM has now withdrawn from the process and Google has pulled out, too,” said a source.

Unfair bias

It is claimed that concerns about the tender being unfairly biased towards AWS were a factor in the suppliers’ decisions to withdraw.

Sources also claimed HMRC had pushed back on supplier suggestions that adopting a hybrid cloud setup might be a better, more cost-effective way to accommodate a migration off-premise, rather than a wholesale move to the public cloud.

This recommendation was given, Computer Weekly understands, on account of how much legacy IT the agency wants to migrate from its three datacentres.

Computer Weekly contacted the Google Cloud team for confirmation of its withdrawal from the tender process, and the reasons why, but was told the company has no comment to make at this time.

The IBM team had not responded to a similar request for comment at the time of publication, despite several attempts being made to contact them.

A spokesperson for AWS also told Computer Weekly it had nothing to share regarding the story.

“So, what you’re left with is a situation where HMRC is going into a half a billion-pound tender process with only one party in the running for it, meaning there is no commercial competition for this contract going on at all,” the source added.

Anti-competition concerns about the contract have been previously raised to Computer Weekly by UK cloud market stakeholders, with objections pertaining to HMRC’s specific request for a “hyperscaler” to deliver the project.

“HMRC is leaving itself wide open to legal challenge given that the term ‘hyperscaler’ is widely associated with the US global cloud players,” said a former government IT advisor, who spoke to Computer Weekly on condition of anonymity, at the time.

The projected length of the project also raised eyebrows, with concerns being raised about the risk of supplier lock-in tied to the contract being 10 years in length.

The notion that AWS is the only supplier left in the running for the contract also comes hot on the heels of the Treasury Select Committee querying HMRC’s reliance on AWS’s US-based infrastructure, after the agency’s operations were disrupted on 20 October 2025 by Amazon suffering a 14-hour outage in its US-based datacentre region.

Computer Weekly put the claims made in this story to HMRC about the other suppliers exiting the procurement process, and also asked for a response regarding the anti-competitive concerns raised about it.

In response, a spokesperson for HMRC said: “We follow government procurement rules when awarding contracts, ensuring a competitive and fair tender process, and value for money for taxpayers. Once contracts are approved, we publish the details on Contracts Finder for transparency.”

According to the government’s own Digital Marketplace figures, which track sales made through the G-Cloud procurement framework, nearly half (45%) of the total £811m in cloud services HMRC has acquired through that purchasing agreement has been spent with AWS, with sales totalling £367.25m.

Sign Up For Daily Newsletter

Be keep up! Get the latest breaking news delivered straight to your inbox.
By signing up, you agree to our Terms of Use and acknowledge the data practices in our Privacy Policy. You may unsubscribe at any time.
Share This Article
Facebook Twitter Email Print
Share
What do you think?
Love0
Sad0
Happy0
Sleepy0
Angry0
Dead0
Wink0
Previous Article Instagram Hooks for SaaS & Service Brands (Even If You Don’t Want to Show Your Face)
Next Article Google calls allegations of ‘secret code’ in international cloud services deal ‘absurd’
Leave a comment

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Stay Connected

248.1k Like
69.1k Follow
134k Pin
54.3k Follow

Latest News

Slowly but surely, high-speed rail backers believe Cascadia mega-project will become a reality
Computing
“I Sweated So Much I Never Needed to Pee”: Life in China’s Relentless Gig Economy
Gadget
The Motorola Razr Ultra is my favorite flip phone, and it’s $400 off
News
iOS 26.1 arrives soon: 4 new features
Software

You Might also Like

News

The Motorola Razr Ultra is my favorite flip phone, and it’s $400 off

4 Min Read
News

Why Felicis’ Newest Partner Focuses On Community Building To Win AI Deals At Seed

10 Min Read
News

PyTorch Foundation Welcomes Ray, Unveils Monarch for Simplified Distributed AI

3 Min Read
News

Don't get too excited about the China tariff cut yet

1 Min Read
//

World of Software is your one-stop website for the latest tech news and updates, follow us now to get the news that matters to you.

Quick Link

  • Privacy Policy
  • Terms of use
  • Advertise
  • Contact

Topics

  • Computing
  • Software
  • Press Release
  • Trending

Sign Up for Our Newsletter

Subscribe to our newsletter to get our newest articles instantly!

World of SoftwareWorld of Software
Follow US
Copyright © All Rights Reserved. World of Software.
Welcome Back!

Sign in to your account

Lost your password?